INVERNESS – FORT WILLIAM CYCLE PATH BRIDGES

PROJECT DESCRIPTION

Design of abutments for short span proprietary bridges on new cycleway; design of accommodation works bridge for estate.

Client – R J McLeod

Completion – 2015

Value – Not Known

AREAS OF RESPONSIBILITY

Site survey; design of concrete abutments / bank pads. Assessment of old railway bridge for inclusion into cycleway.

PRINCIPAL ELEMENTS

  • Reinforced concrete substructure
  • assessment of steel girder and trough railway bridge to BD21
  • Abutments for estate bridge formed from concrete filled manhole rings

KEY FEATURES

Simplified construction methods; limited access to working areas.

CONTRACTORS

Project Manager – Wallace Stone

Main Contractor – R J McLeod