ELGIN FLOOD ALLEVIATION SCHEME
PROJECT DESCRIPTION
Design checks on two temporary proprietary bridges on mass concrete block abutments.
Client – Morrison Construction Ltd
Completion – 2012
Value – N/A
AREAS OF RESPONSIBILITY
Design checks – bridge decks and substructure; checking effect of crane outrigger loads.
PRINCIPAL ELEMENTS
- Design checks for public use and construction vehicles
- Proprietary panel bridges, 33m and 18m span
- Euroblock precast concrete abutment blocks
KEY FEATURES
Temporary bridges constructed for public and contractor access during construction of flood alleviation scheme.
CONTRACTORS
Project Manager – Wallace Stone
Main Contractors – Morrison Construction Ltd