LOCHBOISDALE PORT OF ENTRY PROJECT

PROJECT DESCRIPTION

Design check of proprietary bridge used as temporary diversion.

Client – Morrison Construction Ltd

Completion – 2013

Value – N/A

AREAS OF RESPONSIBILITY

Independent design check of proprietary superstructure and reinforced concrete bankseat abutments.

PRINCIPAL ELEMENTS

  • Three main box girders
  • Span 40.3m
  • Two lane road

KEY FEATURES

Steel box section deck with cross beams and stiffened plate deck.

CONTRACTORS

Project Manager – Wallace Stone

Main Contractor – Morrison Construction Ltd