LOCHBOISDALE PORT OF ENTRY PROJECT
PROJECT DESCRIPTION
Design check of proprietary bridge used as temporary diversion.
Client – Morrison Construction Ltd
Completion – 2013
Value – N/A
AREAS OF RESPONSIBILITY
Independent design check of proprietary superstructure and reinforced concrete bankseat abutments.
PRINCIPAL ELEMENTS
- Three main box girders
- Span 40.3m
- Two lane road
KEY FEATURES
Steel box section deck with cross beams and stiffened plate deck.
CONTRACTORS
Project Manager – Wallace Stone
Main Contractor – Morrison Construction Ltd