KIRKIBOST PONTOONS
PROJECT DESCRIPTION
New pontoon facility for local and visiting boats, with power and water supplies; new facilities building, with toilets, showers, coin operated laundry, and managers office.
Client – Great Bernera Community Development Trust
Completion – 2023
Value – £450,000
AREAS OF RESPONSIBILITY
Feasibility study; survey of seabed and foreshore; layout design; drawings; obtaining tenders; project management; supervision of works, including diving inspection.
PRINCIPAL ELEMENTS
-
Berthing/access pontoon units – 70m
-
Access bridge with shore frame – 24m
-
Electrical bollards with lighting – 7no.
-
Water hose reels – 2no.
-
Chain & Anchor mooring system
-
Insulated facilities building with toilets, showers, laundry and managers office, including underfloor heating
KEY FEATURES
Orientation aligned for minimum wave disruption; potential for future extension with deeper water berths; building heated using renewable solar energy.
CONTRACTORS
Project Manager – Wallace Stone
Pontoons Contractor – Inland & Coastal
Moorings Contractor – North West Marine
Building Contractor – Alex Murray Construction