 
			LOCHMADDY FERRY TERMINAL UPGARDE WORKS
PROJECT DESCRIPTION
The existing pier at Lochmaddy was strengthened to support new fendering for a larger ferry to be used on the route. The pier was also extended with a 33m long concrete caisson constructed in a dry dock. The marshalling yard was enlarged to service the larger number of vehicles for the larger ferry. The berth was dredged to -5m CD, including rock dredging at the existing pier.
Client – Comhairle nan Eilean Siar (Western Isles Council)
Completion – 2023
Value – £18.5 million
AREAS OF RESPONSIBILITY
Preliminary design development; detailed design; tendering; NEC Project Manager and Supervisor during construction.
PRINCIPAL ELEMENTS
- 
Concrete caisson 3500t; Dredge 
- 
5000m³ soft and 300m³ rock 
- 
Rock armoured foreshore for reclamation 2250m³ 
- 
Rock infill 700m³ 
- 
Reclamation 4000m³ 
- 
Bituminous surfacing 2250m²; 
- Caisson infill 3850m³
- 
Caisson concrete slab 200m³ 
- 
Fender support steelwork 150t 
- 
Rock anchors to outer pier 
- 
Parallel motion fenders 15no. 
KEY FEATURES
Strengthening existing pier structures to support new parallel motion fenders; Caisson extension to improve safety of vessel manoeuvring and enhanced berthing capacity for larger ferry; Remote location working around ferry sailings to prevent disruption to service.
CONTRACTORS
Main Contractor – George Leslie
Fendering – Trelleborg
Client Advisor – Caledonian Maritime Assets Ltd (CMAL)
 
				
