LAMLASH PIER AND SLIPWAYS REFURBISHMENT
PROJECT DESCRIPTION
Refacing, resurfacing and refurbishment of existing eroded historic pierhead. Demolition and reconstruction of 10m wide Main Slipway to Chart Datum and 6m Dinghy Slipway to MLWN, in reinforced concrete.
Client – Arran Yacht Club
Completion – 2002
Value – £220,000
AREAS OF RESPONSIBILITY
Conceptual and detailed design of works, project management and site supervision.
PRINCIPAL ELEMENTS
- Main slipway concrete – 230 m³
- Dinghy slipway concrete – 90 m³
- Timber fendering – 195 l.m
- Pierhead concrete – 135 m³
- Deck furniture
KEY FEATURES
Construction of a reinforced concrete facing wall to the existing eroded and undermined sandstone pierhead with new fendering, bollards, ladders and water services. Reconstruction of landing steps. Demolition and reconstruction of two adjacent slipways in reinforced concrete, including new mooring rings and fendering.
CONTRACTORS
Main Contractor – Barr Construction Ltd