LAMLASH PIER AND SLIPWAYS REFURBISHMENT

PROJECT DESCRIPTION

Refacing, resurfacing and refurbishment of existing eroded historic pierhead. Demolition and reconstruction of 10m wide Main Slipway to Chart Datum and 6m Dinghy Slipway to MLWN, in reinforced concrete.

Client – Arran Yacht Club

Completion – 2002

Value – £220,000

AREAS OF RESPONSIBILITY

Conceptual and detailed design of works, project management and site supervision.

PRINCIPAL ELEMENTS

  • Main slipway concrete – 230 m³
  • Dinghy slipway concrete – 90 m³
  • Timber fendering – 195 l.m
  • Pierhead concrete – 135 m³
  • Deck furniture

KEY FEATURES

Construction of a reinforced concrete facing wall to the existing eroded and undermined sandstone pierhead with new fendering, bollards, ladders and water services. Reconstruction of landing steps. Demolition and reconstruction of two adjacent slipways in reinforced concrete, including new mooring rings and fendering.

CONTRACTORS

Main Contractor – Barr Construction Ltd