ULLAPOOL HARBOUR FUEL TANKS

PROJECT DESCRIPTION

Construct tank bund, fuelling slab and drainage; Replace trench covers; Form fuelling points; Fabrication and installation of fuel tanks and associated pipework.

Client – Ullapool Harbour Trust

Completion – 2017

Value – £320,000

AREAS OF RESPONSIBILITY

Design and construction of reinforced concrete bund with upstand walls; Provision of oil interceptor and associated pipework; Design and construction of fuelling slab; Fencing and gates; 4No. service trench spurs; Pipework and delivery system.

PRINCIPAL ELEMENTS

  • Fuel tanks
  • Fuelling points
  • Associated pipework and pumps

KEY FEATURES

Delivery of fuel at a rate of 1000 l/min

CONTRACTORS

Project Manager – Wallace Stone LLP

Main Contractors – Lochshell Engineering

                            – Isleburn