Wemyss Bay Ferry Terminal was successfully re-opened on Good Friday (25th March 2016) following an ambitious programme of repairs, refurbishment and reconstruction. The £5.0M of works were completed during a 6 month closure window which required the main ferry service between the mainland and Bute to be redirected to Gourock. Wallace Stone were responsible for the detailed design and supervision of the pier and fendering works.