Wallace Stone has been working for Contractor, George Leslie, on the detailed design of this project and the first stage has now been completed. The basin has been dredged and the reclaimed materials have been used to form a car park and slipway. A 60m culvert extension, along with rock armouring and retaining walls, has also been constructed.
The construction of an 18 x 7m building is due to start on 23 November 2020. This will house marina facilities, including toilets, showers and a café.